PARBAT: With the completion of the project development, Setikhola Hydropower Project in Paiyun and Bihadi rural municipalities in Parbat district has started power generation.
The project with a capacity of 3.5 megawatts (MW) has also started its test transmission, completing the entire development work in five years.
The canal headwork of the project is at Beulibas of Paiyun Rural Municipality-2 while the powerhouse is at Ghangre of Bihadi Rural Municipality-6. The water has been supplied to Ghangre through a 3,600-metre-long pipeline from Beulibas.
China's Asia Pacific Project carried out the electromechanical job of the project while K and K Builders from Biratnagar carried out the pipeline works.
Company Secretary of the project, Shiva Shankar Basyal, said that The Brothers Builders Kathmandu was assigned to build the civil construction of the project. It is said that the total cost of the project has exceeded Rs 1.1 billion.
Basyal shared that the power generated from the project will be supplied to the national grid of Nepal Electricity Authority (NEA) in two weeks adding that the power purchase agreement (PPA) has already been signed with the NEA.
Siddhartha Bank Ltd and Garima Development Bank have invested in the project.